If you had 6 hours of load testing to complete...

  • perf-test.com need your contributions to build up a strong repository of performance engineering resources.

S

Sakshi Naik

Guest
If you had 6 hours of load testing to complete but the business unit wanted it turned over in 3 hours what would you tell them?
 
You mean to say that the test completed in 3 hours?
 
Complete the testing for 3 hours and pull a graph for 6 hours and make it clear ex: if the result is 100 for 3 hours , the u can say PROBABLY for 6 hours it will 200 (more or less) ... but communication should be clear on this